Have your combustion turbines been losing power after overhauls? There are many factors which can affect power production, but the IGV settings are one area that even the OEM can overlook.
We recently helped a plant with three GE Frame 6B gas turbines that had lost power over successive overhauls. Units 1 and 2 had been overhauled by the OEM in the last few years and Unit 3 had been overhauled in 2006 by a competitor. All three units had been experiencing an unexplained loss of power.
A gas turbine needs to breathe air – and a lot of it – to make horsepower. The inlet guide vanes (IGVs) on a heavy duty gas turbine are designed to modulate (open and close) in response to commands from the control system to regulate this air flow. These commands control turbine exhaust temperature, protect against a compressor “stall” or “surge” (extremely damaging to the compressor blading), and other controlling functions. The IGVs look like little airplane wings that rotate or pivot to allow more or less air into the compressor. They are calibrated to the turbine control system by measuring the actual vane angles with a machinist’s protractor and inputting the readings into the control system. This lets the electronic controls know physically where they are so that the system can properly control the unit.
On checking Unit 1 and 2, the IGV calibration was significantly out of calibration. Unit 3 wasn’t as bad but it was also slightly out of calibration., We accurately calibrated the IGV’s to the OEM control specifications on all three units.
The results of this work were impressive. The heat rate (fuel efficiency) improved on Unit 1 by about 2%, gained 2.5 mw on Unit 2 and 0.5 mw on Unit 3. This made a significant contribution to the customer’s bottom line at the expense of just a few days of work.
The IGV calibrations are just one of the critical instruments or calibrations that could affect power production. Contact PSG® for a full analysis of any reductions to the heat rate or power output of your turbine
Project Spotlight – Steam Turbine Diaphragm Restoration
/in Project Spotlight /by Mike.LakeDuring the spring outage season Power Services Group was contacted by an Industrial Steam Turbine Owner in the Midwest with the intent to purchase a new diaphragm assembly (upper and lower halves). The customer was advised by the OEM that their existing diaphragm assembly was beyond economical repair. The lead time and price provided by the OEM to manufacture a new diaphragm assembly would have put the customer over budget and beyond the allotted schedule for their planned outage in progress.
In response to the customer purchase inquiry, we requested photos of the damaged areas of the existing diaphragm. After a detailed review we informed the customer that the existing diaphragm assembly could be repaired at a reasonable price and schedule.
After the customer reviewed our detailed repair plan and schedule, they accepted the proposal and personally delivered the diaphragm assembly to our Midwest Repair Center of Excellence located in Pevely, Missouri.
After incoming inspection, our technicians executed a major weld repair of the admission and exhaust side inner and outer setback faces of both diaphragm halves. Upon completion, final dimensional inspections were performed. After thorough quality verification, the diaphragm assembly was expedited back to the customer’s facility, successfully installed, and returned to service.
The total schedule for all work completed – from receipt of initial phone call to a fully-repaired, delivered diaphragm assembly – was 11 days. This timeline was not considered possible by the customer when they initiated that first call.
PSG provided the customer an alternative, attractive solution they thought was unattainable. The diaphragm assembly was restored, instead of replaced, at much lower cost than a new diaphragm assembly. Even more importantly, extensive repairs were completed within 11 days of initial contact, versus the long lead time of new component manufacturing. PSG saved the customer significant downtime and associated lost production revenue. We are proud to have a satisfied customer we were able to help through an extremely difficult situation.
“As Found” Photos:
Exhaust-Side Erosion
Admission-Side Erosion
“As Left” Photos:
Admission Side Final Machined
Exhaust Side Final Machined
Horizontal Joint Final Machined
Horizontal Joint Final Machined
Finished Diaphragm
Frame 7EA Users Group Conference
/in Events /by Mike.LakePSG will be exhibiting at this year’s Frame 7EA Users Group Conference in Garden Grove, California on Tuesday, October 9th. We will be at Booth #46 and are looking forward to discussing our recent 7EA projects with you. Safe Travels and see you in California!
Set IGVs for Maximum Efficiency
/in Combustion Turbine Tips /by Mike.LakeHave your combustion turbines been losing power after overhauls? There are many factors which can affect power production, but the IGV settings are one area that even the OEM can overlook.
We recently helped a plant with three GE Frame 6B gas turbines that had lost power over successive overhauls. Units 1 and 2 had been overhauled by the OEM in the last few years and Unit 3 had been overhauled in 2006 by a competitor. All three units had been experiencing an unexplained loss of power.
A gas turbine needs to breathe air – and a lot of it – to make horsepower. The inlet guide vanes (IGVs) on a heavy duty gas turbine are designed to modulate (open and close) in response to commands from the control system to regulate this air flow. These commands control turbine exhaust temperature, protect against a compressor “stall” or “surge” (extremely damaging to the compressor blading), and other controlling functions. The IGVs look like little airplane wings that rotate or pivot to allow more or less air into the compressor. They are calibrated to the turbine control system by measuring the actual vane angles with a machinist’s protractor and inputting the readings into the control system. This lets the electronic controls know physically where they are so that the system can properly control the unit.
On checking Unit 1 and 2, the IGV calibration was significantly out of calibration. Unit 3 wasn’t as bad but it was also slightly out of calibration., We accurately calibrated the IGV’s to the OEM control specifications on all three units.
The results of this work were impressive. The heat rate (fuel efficiency) improved on Unit 1 by about 2%, gained 2.5 mw on Unit 2 and 0.5 mw on Unit 3. This made a significant contribution to the customer’s bottom line at the expense of just a few days of work.
The IGV calibrations are just one of the critical instruments or calibrations that could affect power production. Contact PSG® for a full analysis of any reductions to the heat rate or power output of your turbine
Enter to Win a 30 oz. YETI Rambler!
/in Events /by Mike.LakeAll you need to do is take a photo of Mr. Turbine somewhere – at your facility, in a restaurant, at an event, on vacation, etc… use your imagination! Once we receive your photo we will enter you to win a 30 oz. YETI Rambler at our next drawing. All photos should be submitted to [email protected] by September 30th, and we will do a random drawing on October 1st for three winners. If you are one of the winners, we will ship the YETI directly to your address. Just snap a photo and send it via email and you’re entered to win!
Here are some other places Mr. Turbine as been spotted recently:
ANS Utility Working Conference & Vendor Technology Expo
/in Events, News /by Mike.LakeWe look forward to seeing everyone at this year’s ANS Utility Working Conference & Vendor Technology Expo in Amelia Island, Florida. It should be another fun event. Please stop by the Power Services Group booth in the exhibit hall when you get a chance. Mike Ballard will be in attendance representing PSG and will be looking forward to meeting everyone.
We will be raffling off a YETI Cooler at the booth, please drop off your business card for a chance to win.
Safe Travels and see you next week!
AEP Go Forum
/in Events /by Mike.LakeStop by and visit us at the AEP Go Forum!
Stationary Blade Restoration
/in Project Spotlight /by Mike.LakeDuring the most recent outage season, PSG was contracted to perform the in-place restoration of stationary blades on an 800MW Steam Turbine for a large power producer in the United States. The customer was looking for a solution where the blades could be restored without completely disassembling the unit and sending the components to a shop – enabling them to save valuable generation time and significant expense. Our Field Machining Division mobilized our specialized technicians and equipment and began the detailed process of restoring the blades, ultimately returning them to operating specifications.
The customer was extremely pleased with the outcome of the project and commented on the high-quality craftsmanship displayed by our technicians. This is another example of the complicated turbine repairs we can perform on-site, and a testament to the quality of our execution personnel.
Measure the Cause, Not the Symptom
/in Steam Turbine Tips /by Mike.LakeDirectly measuring bearing metal temperature is the most effective way to really determine if a bearing is running hot. Bearing oil drain temperatures are still being utilized on older machines. By the time the bearing oil drain temperature has increased, the bearing may have already been compromised (wiped). PSG recommends that these older machines should have temperature probes (thermocouples or RTD’s) installed in the bearing Babbitt to properly monitor performance. A two-level alarm is recommended (not automatic trip). The first alarm should be set a few degrees above the highest temperature in the recommended normal operating range. Operators should closely monitor bearing temperature after the first alarm sounds. If the temperature rises abruptly and unexpectedly, the bearing may have been compromised and immediate action needs to be taken. Gradual temperature changes which trigger the alarm may be the result of other factors but are still a concern and should be thoroughly investigated. The second alarm should be set at the maximum operating temperature of the bearing material. Operators should manually trip the unit in a controlled manner as soon as possible after this second alarm sounds and determine the cause. The critical temperatures for each of the two levels can be supplied by the manufacturer or recommended by PSG for your individual unit configuration. Different temperature ranges are recommended for Tilt Pad, Elliptical, Short Elliptical and Thrust bearings. Measuring drain oil temperature is too slow and too imprecise to effectively minimize your overall cost of maintenance. Retrofit your machine and save your bottom line.
Spill Strip Installation
/in Project Spotlight /by Mike.LakeWe are in the process of installing new spill strips for an industrial GE Steam Turbine. Very nice work by our Steam Path Repair facility in Pevely, Missouri.